25. |
2021-0267 AUTHORIZE:
A. The Chief Executive Officer (CEO) to award and execute a three (3) year contract, Contract No. AE70151EN085, with Arcadis US, Inc. for Environmental Services and Construction ... Approved |
View
|
Download
|
26. |
2021-0423 RECEIVE AND FILE status report on Program Management quarterly change report. Received |
View
|
Download
|
27. |
2021-0405 RECEIVE AND FILE Office of the Inspector General Change Order Construction Spot Check Report for the period March 1, 2021 to May 31, 2021. Received |
View
|
Download
|
28. |
2021-0431 RECEIVE oral report on the Major Project Status by the Chief Program Management Officer. Received |
View
|
Download
|
|
2021-0475 RECEIVE General Public Comment None |