20. |
2016-0156 RECEIVE Program Management Executive Director’s oral report. Received |
View
|
Download
|
21. |
2015-1390 CONSIDER:
A. INCREASING the Life of Project (LOP) and Contract Modification Authority (CMA) as follows:
1. LOP Budget for Patsaouras Bus Plaza Station (PBPS CP 202317) by $8,809,000, from ... Approved |
View
|
Download
|
22. |
2016-0098 AUTHORIZE the Chief Executive Officer to:
A. AWARD a cost-plus fixed fee Contract No. AE4569400 for Construction Management Support Services for Soundwall Package No. 11 with Ghirardelli ... Approved |
View
|
Download
|
23. |
2016-0134 APPROVE:
A. INCREASING the Life of Project Budget (LOP) Budget for Metro Red Line Universal City Pedestrian Bridge (CP 809382) by $2,285,000 from $27,300,000 to $29,585,000;
B. INCREASING ... Approved |
View
|
Download
|